08/10/2026
Gash's report is the second in a series of expert reports on Yntegra’s Rosewood Exuma project that we are releasing over the coming weeks.
Mark Gash, Director of Turnstone Ecology Limited and a Full Member of the Chartered Institute of Ecology and Environmental Management, was instructed to provide an independent review of the two documents at the centre of Yntegra's approvals: the Environmental Impact Assessment (EIA), which is required by the Department of Environmental Planning and Protection (DEPP) to explain how a project will affect the environment, and the Environmental Management Plan (EMP), which is meant to set out how those impacts will be minimised. He examined the adequacy of the ecological assessment as a whole, with particular focus on the bird surveys, and measured it against two internationally recognised benchmark
Gash found that Yntegra’s EIA submitted in support of its Rosewood Exuma project and the survey programme behind it, he writes, are "wholly inadequate for a site of this ecological sensitivity” and he expressed concern that “major adverse impacts that cannot be mitigated or offset" if Yntegra were to go ahead with the project as planned.
Among other issues, he found that the site, on the available evidence, is "highly likely to qualify as Critical Habitat under multiple IFC PS6 and ESS6 criteria yet no Critical Habitat assessment was carried out at all” before or after approvals were given.
You can read a summary of the report and the full report on our website at the following link: https://www.turtlegrassresort.com/blog/an-expert-found-yntegras-environmental-case-for-sampson-cay-wholly-inadequate