𝐒𝐇𝐎𝐑𝐓 𝐃𝐄𝐋𝐀𝐘 𝐓𝐎 𝐌𝐀𝐑𝐈𝐍𝐄 𝐆𝐀𝐑𝐃𝐄𝐍𝐒 𝐏𝐋𝐀𝐙𝐀 𝐇𝐀𝐍𝐃𝐎𝐕𝐄𝐑
Bangor’s new Marine Gardens plaza is now expected to be handed over to the Council on 11th November, following a problem with the electricity substation serving the site.
The handover was planned for 30th October, but councillors have been reassured there should still be enough time to prepare the space for its first Christmas celebrations.
Explaining the delay, Council director Brian Dorrian said parts of the substation installed by NIE were “not correct”. He told members that NIE had openly accepted responsibility and was working tirelessly to put things right.
The aim is to have the substation working by 6th November. Bangor Marine and the Council’s team would then carry out the final checks, with handover hoped for on 11 November.
Once the Council takes over the plaza, attention can turn to welcoming people into the new space. Mr Dorrian said public access should follow soon afterwards, with time allowed to install the new Christmas tree and make the other festive preparations.
There was welcome news about the facilities beside the plaza too. Councillors were told that the newly refurbished toilet block at the McKee Clock will also be ready for the Christmas event, providing a much-improved amenity for families and visitors enjoying the celebrations.
Councillor Alistair Cathcart welcomed the progress around the McKee Clock, recalling that during his time as mayor he had wondered whether work on the site would ever begin.
He also praised the Christmas plans, which are expected to include music and lights across several evenings, giving people more opportunities to come down and enjoy the atmosphere.
After watching the plaza take shape over the past year, many will be looking forward to that first stroll around it, with the Christmas celebrations offering a chance to gather and enjoy Bangor’s changing seafront together.